Our contractors will be conducting resurfacing works to several roads in the estate in early to mid July. These proposed works are weather dependent, and require preparatory work to be carried out beforehand.
Please note any dates below which may apply to you. If you have neighbours who are unlikely to receive notice by email please could you tell them or otherwise draw it to our attention?
PROPOSED SCHEDULE:
- WEDNESDAY 13TH JULY – Winkers Close, preparatory work
- THURSDAY 14TH JULY – Lewis Lane & Sandy Rise, preparatory work
- FRIDAY 15TH JULY – Half Acre Hill, some preparatory work; install gully and soakaway
- MONDAY 18TH JULY – Half Acre Hill, remaining preparatory work.
- MONDAY 18TH JULY – Lower Chiltern Hill, preparatory work
- TUESDAY 19TH JULY – Lower Chiltern Hill and Half Acre Hill, resurfacing
- WEDNESDAY 20TH JULY – Lewis Lane and Sandy Rise spur, resurfacing
- THURSDAY 21ST JULY – Winkers Close, resurfacing
- FRIDAY 22ND JULY – Lincoln Road hump and tidy up
On the days of preparation and surfacing, residents will have only limited access to their properties: you are kindly asked to consider alternative parking arrangements on those days.
Residents of Half Acre Hill will have very limited access, probably pedestrian only, on Fri 15 when the gully and drainage is installed. A location needs to be identified for Half Acre Hill’s bins on Fri 15 July.
Could you please let us know via [email protected] if there any ongoing building works around the estate that might be affected by the planned road resurfacing works?
Weather conditions are likely to affect the surfacing days more than the preparation days.